Harvey St. Construction Update October 1, 2021
Published on Oct 1, 2021 11:56
Friday October 1, 2021
The beginning of a new month and we are nearing approximately one
month until completion of the Harvey St. construction. There has been
significant progress on many portions of the project, but still a ways
to go until the project is complete.
This last Wednesday, a sign that we are beginning to inch closer to
the end was installed and that was curbs on Harvey between Fleet St. and
Ann Arbor Trail. It is expected that beginning next week, the next
phase on concrete work will begin and that will be work that takes place
behind the curb. Drive approaches and sidewalks will begin being
installed in that same stretch. As with all concrete work, please
exercise caution and avoid the area if at all possible to give the
concrete proper time to cure.
Ruahorn Electric continues setting the foundation, bases, and
installing the conduit for the new mast arms and pedestrian crossing
signals in the intersection at Ann Arbor Trail and Harvey. Once their
work is complete, crews will return to install curb, sidewalk, etc.
Please note that due to the lengthy lead time on the materials for the
mast arms, etc. it is anticipated that the final installation will occur
in the Spring. Until then, the current traffic signals will still be in
operation.
The most difficult portion of the project is underway in the
intersection of Penniman and Harvey and that is the underground utility
work. Today, crews will make the first two connection of the new water
main on Harvey to the current water system. Those residents and
businesses affected by todays work were hand delivered notices about the
temporary interruption. Early next week, there will be another
connection, although it is planned to be late in the day/early evening
so as not to impact as many businesses. Again, City staff will be hand
delivering notices to those affected water customers.
Crews will also continuing working on the storm sewer and sanitary
sewer systems I the intersections; repairing and replacing as necessary.
Depending on how the rest of today goes, will determine if the crews
work on Saturday to try and get as much done while the weather
cooperates.
The intersection of Penniman and Harvey is the biggest challenge for
the vast amount of underground utilities as well as the difficulty in
detouring the traffic around. We are doing our best in assisting traffic
with flag people, and trying to keep open as much as we can as long as
its safe for the crews and the drivers, and pedestrians. We ask for your
patience over this next week as we work to complete the work in the
intersection. If you can seek alternate routes, we recommend doing so to
save yourself some time in getting through and also keeping the work
area safe by having fewer cars and pedestrians in or near the work area.
In addition, we have prepared a diagram showing the detour route
while the intersection of Ann Arbor Trail and Harvey, as well as the
intersection at Penniman and Harvey is closed to through traffic. You
can view that map, by clicking on the following link: 2021 Ann Arbor Trail and Harvey Detour Map.
Should you have any questions, please contact the Department of Municipal Services at 734-453-7737 or [email protected]
|